The £3m contract in Swindon includes a groundworks package for foundations and drainage, which are presently underway. The new building will provide storage for the museums artefacts and is being constructed on the track that is famous for Jeremy Clarkson’s “Grand Tour” series.
McCoy’s Project Manager, Ryan Nuss said: “The project is progressing well, we have recently completed the foundations. The installation of the precast ground beams, storm and foul drainage and construction of the lift shaft are underway, work will continue on these areas over the next few weeks.